On November 3, 2026, data centers were on local ballots in 10 US states and at the center of several governor's races, and voters sided with limits almost everywhere. In the same weeks, developers announced tens of billions of dollars of new campuses elsewhere. Here is what was decided, what was only promised as of November 16, 2026, and what both mean for the price of a server or a rack.
What voters decided
Ballotpedia, the count CNBC also used, lists 41 local data center measures on November 3, 2026, 21 of them in Ohio, and found voters favored limits in 40: 27 measures restricting or opposing development passed and 13 that would have helped projects failed. The exception was Harwood, North Dakota, where voters defeated an added review requirement for industrial projects.
Other tallies differ, partly by cut-off and definition: Bloomberg Economics counted 46 measures approved or on track to pass, Redbud Consulting (cited by CBS News) counted 38 approved as of November 4, 2026, and a Tom's Hardware headline put 45 on the ballot.
| Place | Measure | Unofficial result |
|---|---|---|
| Grove City, Ohio | Issue 28: citywide vote required for large projects, including any over 20 MW | Passed, 54.6% |
| Trenton, Ohio | Charter ban above 25 MW | Passed, about 80% |
| Piqua, Ohio (proposed Meta site) | Charter ban above 25 MW; recall of three city commissioners | Passed, about 67%; all three recalled, at least 70% each |
| Sunbury, Ohio | Charter ban above 25 MW | Passed, about 79% |
| Hubbard, Ohio | Ban on all data centers in city limits | Passed, about 76% |
| Perry, Ohio | Financial guarantees from developers seeking tax incentives; noise limits | Passed, about 87% |
Every figure above is unofficial as of November 16, 2026. Ohio's 2026 elections calendar requires county boards to begin the official canvass by November 18, 2026 and complete it by November 24, 2026. Results elsewhere are likewise subject to canvass and certification.
Two Texas items often listed with the ballot results were city actions, not public votes: San Marcos effectively barred data centers by a 4-3 council vote on June 16, 2026, and Brownsville approved a 90-day moratorium on applications that took effect in the first week of November 2026.
Decided versus promised
Decided, and in force or awaiting certification:
- The local measures bind only the places that passed them; most Ohio bans apply above 25 MW.
- On November 3, 2026, the Florida Public Service Commission voted 5-0 to reject Duke Energy Florida's tariff for large data center loads because it did not show compliance with SB 484, the 2026 law requiring large-load customers to bear their full cost of service. Duke can file again.
- In Georgia, Democrats won both Public Service Commission seats on the ballot and hold three of five, per King & Spalding.
- In Texas, Governor Greg Abbott's directives of August 3 and September 21, 2026 had already paused grid connections and environmental permits pending an ERCOT audit; data centers under 25 MW are exempt.
Promised, and still needing an order or a bill:
- Texas governor-elect Gina Hinojosa said she would issue a moratorium on "all data center approvals" until the Legislature passes new laws. The Legislature convenes on January 12, 2027; she takes office on January 19, 2027.
- Ohio governor-elect Amy Acton, who takes office in January 2027, backs a "conditional moratorium" unless developers cover 100% of utility costs, among other conditions. Signal Cleveland reported in July 2026 that it was unclear which parts need the Republican-controlled legislature.
- Ohio House Bill 646, which would have the Public Utilities Commission of Ohio establish a data center rate class, stalled in June 2026. The Ohio Capital Journal reported on November 16, 2026 that legislative leaders had not ruled out lame-duck action.
Cleanview, cited by Bloomberg, calculated that about 40% of pending US data center capacity is planned in states whose newly elected governors promised to stop or pause construction: Ohio, Georgia, Michigan, New Mexico and Texas.
The build-out in the same weeks
- Google confirmed its interest in about 1,000 acres in Goochland County, Virginia, tied to a 1,200 MW campus, with no plans filed as of October 28, 2026. On November 5, 2026, it announced a $17 billion data center in Laramie County, Wyoming, near Cheyenne, with a 702 MW fuel cell plant.
- Lambda said on November 4, 2026 that it will anchor the $33.1 billion Red Clay Technology Center Campus in Lowndes County, Alabama, with construction expected in the first quarter of 2027.
- Fluidstack had broken ground by October 28, 2026 on a 99-acre campus in Wythe County, Virginia, targeting operation by the end of 2027.
- DTE Energy, the Michigan utility, set a $44.2 billion investment plan for 2027 to 2031, citing data center demand that includes contracts with Google and Oracle.
- Two went the other way. Prometheus Hyperscale dropped its Casper-area project in Wyoming on October 28, 2026, saying other Wyoming locations "offer a clearer path to permitting and community support". IREN said on November 5, 2026 that some Microsoft deliveries in Texas slipped after Microsoft requested network design changes.
What this does to a server or rack bill
The votes landed in a full market. CBRE's H1 2026 report put primary-market vacancy at a record-low 1.4%, with 80.4% of capacity under construction preleased. Asking rates rose in every size band:
- 250 to 500 kW: up 4.3%
- 500 kW to 3 MW: up 7.9%
- 3 to 10 MW: up 8.3%
- 10 MW and above: up 6.7%
JLL's 2026 outlook puts the average wait for a grid connection in primary markets above four years; our piece on power, cooling and density covers why.
How the votes reach a bill:
- The rules aim at new, large loads. Most of the Ohio bans start at 25 MW, and AEP Ohio's tariff, approved by state regulators on July 9, 2025, makes new data center customers above 25 MW pay for at least 85% of subscribed capacity for up to 12 years. An existing hall selling racks or dedicated servers is not new load. The October industry roundup covered federal bills drawing similar lines at 20 MW and 100 MW.
- New supply slows later, not at once. Renewable Energy World reported that projects under construction, permitted or holding interconnection agreements will likely proceed, and cited analysts, via Axios, who say as much as 60% of planned 2028 projects could face delays. If that holds, existing powered space in a constrained market gets scarcer relative to demand, with less new supply to pull rates back.
- Power costs reach a bill through the contract. Rate classes are designed to keep large-load costs off other customers, which favors a small facility on a general tariff. Where a rate case does raise a facility's cost, the pass-through clause decides whether the customer pays. Where the money goes in a data center shows how large the energy line can be.
What to ask a provider before January 2027
- Power billing: is power metered or flat? Which utility charges can be passed through, at cost or with a markup, and is there a cap?
- Notice: how many days of notice apply to a price change, and is there an exit right above a set increase?
- Term: a longer term fixes the base rate, but check whether pass-through items still float inside it.
- Location: which building, utility, city and state hold the capacity? Ask whether that jurisdiction has a pause, a size cap or a rate case pending, such as Ohio's HB 646, a refiled Duke tariff in Florida or the Texas session opening on January 12, 2027.
- Expansion: ask for a right of first refusal on adjacent space and power priced in writing, because most capacity under construction is already leased.
Sources
- Ohio Secretary of State: 2026 Ohio Elections Calendar (PDF, hosted by the Hamilton County Board of Elections)
- Ballotpedia News: Voters favored limiting data center development in 40 of 41 local ballot measures on Nov. 3
- CBRE: North America Data Center Trends H1 2026
- JLL: 2026 Global Data Center Outlook
- Google: Investing in Wyoming's infrastructure, energy and workforce
- Lambda: Lambda to build new data center in Lowndes County, Alabama, investing more than $33 billion in state
- AEP: AEP Ohio Proposal on Data Centers to Protect Ohio Consumers Adopted by PUCO
- King & Spalding: Navigating New Headwinds, What the 2026 Election Results Mean for Data Center Projects in Texas, Ohio, and Georgia
- Venable: Voters Approve Data Center Restrictions at the Ballot Box
- CNBC: data center ballot measures in the 2026 midterms, November 4, 2026
- Insurance Journal (Bloomberg): Some 40% of Planned Data Center Capacity Is in States Wanting to Hit Pause
- WOSU: Here's how every data center-related ballot measure fared in Ohio
- Fox 8: How Northeast Ohio voted on data center issues in the Nov. 3 general election
- WHIO: Meta revealed as company behind proposed Piqua data center
- Yahoo News (Florida Phoenix): Florida Public Service Commission rejects Duke Energy's data center plan
- Spectrum News 13: Florida Public Service Commission rejected Duke Energy Florida's proposal for handling cost tied to data centers
- KSAT (Texas Tribune): Gina Hinojosa won the governor's race, what happens to Texas data centers
- Texas Tribune: SpaceX data center and power plant near Brownsville, November 10, 2026
- Route Fifty (Texas Tribune): San Marcos becomes the first Texas city to ban data centers, testing its local control
- Yahoo News (Ohio Capital Journal): Will Ohio lawmakers pass data center legislation during lame duck?
- Statehouse News Bureau: Ohio lawmakers introduce, may advance data center bill within 48 hours
- Signal Cleveland: Amy Acton's Ohio data center plan
- CBS News: Midterm elections could zap the data center buildout, experts say
- Renewable Energy World: Voters overwhelmingly rejected data centers in the midterms, here's where developers will have a tough time
- Tom's Hardware: AI data centers comprehensively defeated at US midterm elections, 45 measures put on the ballot
- Richmond BizSense: Google eyeing data center campus in Goochland's West Creek
- TNW: Google's first Wyoming data centre will run on gas with carbon capture
- WDBJ: Fluidstack hosts open house for Wythe County data center
- Utility Dive: DTE expands 5-year electric investment plan, sells unregulated Vantage
- Cowboy State Daily: Prometheus Abruptly Drops Natrona Data Center Plan, Eyes New Wyoming Locations
- The Star (Reuters): AI data center firm IREN delays Microsoft AI deliveries, plans $15 billion spending push
- Data Center Frontier: CBRE, Record Data Center Construction Fails to Ease Capacity Crunch
- Mission Critical News, November 5, 2026 (roundup used to locate original reports)
- Mission Critical News, November 9, 2026 (roundup used to locate original reports)
- dataxconnect weekly data centre news, November 6, 2026 (roundup used to locate original reports)