Two very different businesses are called "data centers". One is a gigawatt AI campus where the electricity bill is roughly fifteen times the payroll. The other is the hosting, colocation or managed-services company most people actually buy servers from, where payroll is the biggest line on the books. Knowing which one you are dealing with explains the price list.
What a gigawatt AI campus spends
Epoch AI published a total-cost-of-ownership model for a one-gigawatt AI data center on May 14, 2026. Its headline: "Servers account for 60% of the total cost of ownership of a one-gigawatt AI data center." The campus "requires $38 billion in up-front capital expenditure (CapEx)" and "$0.9 billion in annual operating expenses (OpEx)." Annualized over each asset's life, "the total cost of ownership equates to $8.5 billion per year," of which servers (modelled as NVIDIA GB200 NVL72 systems) are about $5 billion.
The up-front capex of $37,883 million breaks down as servers $21,188M, facility $11,433M, network infrastructure $4,925M, land $172M and utility works $164M. The operating budget answers the people question:
| Annual OpEx line (Epoch AI, 1 GW campus) | $ millions per year | Share of $907M OpEx |
|---|---|---|
| Energy | 594 | 65% |
| Taxes | 143 | 16% |
| Maintenance | 120 | 13% |
| Labor | 40 | 4% |
| Water | 6 | under 1% |
Rows are rounded by Epoch and sum to $903M against the stated $907M. Land ($13M) and utility works ($20M) are carried as annualized capex, not opex.
The assumptions behind the energy line are the ones that matter at this scale: electricity at 8.34 cents per kWh (a weighted 2024 EIA industrial average), a PUE of 1.14 and 71% utilization. Server life is the other lever: Epoch's base case is five years; three years pushes the annual total to about $12 billion, seven years to about $7 billion. Labor at $40 million is 4% of opex and under half of one percent of the $8.5 billion total. Automation, PUE and the power contract decide the economics; headcount barely registers.
JLL's 2026 Global Data Center Outlook (January 5, 2026) corroborates the split. It forecasts average construction cost rising 6% to $11.3 million per MW in 2026, shell and core only, and notes that "tenants are typically responsible for the tech fit-out which can cost as much as $25 million per MW for AI infrastructure." Epoch's facility line works out to $11.4 million per MW, and its servers plus network to $26.1 million per MW.
Where the people are: building it, not running it
The labor in an AI campus is front-loaded into construction. Associated Builders and Contractors' January 15, 2026 release says "the construction industry needs to attract an estimated 349,000 net new workers in 2026," and that "in 2027, the industry will need to bring in 456,000 new workers to meet demand." ABC adds that "demand for electricians capable of precision wiring has surged due to the rapid increase in data center construction," and that missing the target would place "further upward pressure on labor costs."
Flagship sites show the shape of it. An Oracle fact sheet dated September 23, 2025 (published by Rep. Jodey Arrington's office) describes the Abilene, Texas campus as "eight buildings on 1,100 acres" with "more than 6,400 construction workers on site every day," while "ongoing, the campus and nearby expansion will provide nearly 1,700 jobs onsite." By March 5, 2026, Crusoe senior vice president Jamie McGrath told Abilene leaders "about 9,000 craft workers are on-site every day." Thousands to build, a fraction of that to run.
The hosting business is the inverse
DigitalOcean's 10-K for the year ended December 31, 2025 reports revenue of $901.4 million, cost of revenue of $361.8 million (40% of revenue), research and development of $161.6 million, sales and marketing of $82.4 million and general and administrative of $138.5 million, for total operating expenses of $382.6 million (42% of revenue). It had 1,462 employees at year end. Per the filing, cost of revenue "consists primarily of fees related to operating our data center facilities," plus support and facilities personnel, partnership expenses and depreciation; research and development expenses "consist primarily of personnel costs," and sales and marketing expenses "consist primarily of personnel costs of our sales and marketing and customer success employees." Even at a self-service cloud, the personnel-dominated lines exceed the entire infrastructure bill, before counting the support and operations staff inside cost of revenue.
| 1 GW AI campus (Epoch AI model) | Self-service cloud (DigitalOcean, FY2025) | |
|---|---|---|
| Largest annual cost | Servers, about $5B of $8.5B (60%) | Cost of revenue, $361.8M of $901.4M (40%) |
| People | Labor $40M, 4% of opex | R&D, S&M and G&A $382.6M, 42% of revenue; R&D and S&M "primarily personnel costs" |
| Energy | $594M, 65% of opex | Not broken out; sits inside cost of revenue |
| Headcount | Not stated; derived from a BCG analysis | 1,462 employees |
| What moves the number | Power price, PUE, server lifespan | Wages, hiring and retention |
BLS Occupational Outlook data for May 2025 gives a median annual wage of $99,130 for network and computer systems administrators (323,600 jobs), $76,220 for computer network support specialists and $61,860 for computer user support specialists. BLS has no "data center technician" category; those roles fall across these and the trades. The market is tight: Uptime Institute's Global Data Center Survey 2025 (July 2025) found "nearly half (46%) of operators report difficulties finding qualified candidates for vacant roles, and more than one in three (37%) struggle to retain their staff." Uptime's October 2025 staffing survey found 55% of organizations increased salary spending over the prior 12 months, with the highest turnover (57%) among operations junior/mid-level staff. Only 22% of operators see AI as a way "to reduce average staffing levels."
There is an efficiency gap too: Uptime's respondents reported a weighted average PUE of 1.54 in 2025, against the 1.14 Epoch assumes. A small operator pays more per useful kilowatt and cannot make it up on headcount, because headcount is what it sells. The facility side is in our piece on power and cooling.
What this means when you buy a server
The difference between a cheap unmanaged box and a managed one is almost entirely people. Hardware, rack space, power and bandwidth cost the provider about the same either way; what changes is who answers at 3 a.m.
- One staffed 24/7 seat is 168 hours a week, or 4.2 full-time equivalents on 40-hour weeks. At the BLS median for a network support specialist that is roughly $320,000 a year in base pay for one seat, before benefits, tooling or management. That is the arithmetic behind support tiers, response-time SLAs and hourly remote hands.
- Unmanaged buys hardware amortization, space, power, bandwidth, a network drop and hardware replacement. Expect remote hands billed by the hour or ticket, and nobody looking at your OS.
- Managed rents you a slice of those 4.2 FTEs: patching, monitoring, backups, security updates and a response commitment. The uplift is labor, which is why it scales with the SLA rather than the server spec.
- When comparing offers, ask what "managed" covers (OS only, or the stack), the response and resolution times, the remote hands rate, whether restores are included, the hardware replacement window, and whether the provider owns the facility (and so its PUE and power contract) or resells someone else's.
At gigawatt scale the question is cents per kilowatt-hour. At the scale most of us operate, it is dollars per hour of a qualified person's time, and the price list is that number rearranged.
Sources
- Epoch AI: Total cost of ownership of a one-gigawatt AI data center
- DigitalOcean Holdings, Inc. Form 10-K for fiscal year 2025 (SEC EDGAR)
- BLS Occupational Outlook Handbook: Network and Computer Systems Administrators
- BLS Occupational Outlook Handbook: Computer Support Specialists
- ABC: Construction Industry Must Attract 349,000 Workers in 2026 Despite Macroeconomic Headwinds
- Uptime Institute Global Data Center Survey 2025 (PDF)
- Uptime Institute: Data Center Staffing and Hiring Survey Findings, October 2025 (PDF)
- Oracle Fact Sheet: Stargate Data Centers, September 23, 2025 (via Rep. Jodey Arrington)
- JLL: 2026 Global Data Center Outlook
- KTXS: Construction on Stargate One data center campus set to run through early 2027