Aurora, Colorado did not ban data center construction on November 23, 2026. That Monday its City Council adopted Resolution R2026-146, a temporary moratorium on new development applications for data centers across most of the city, lasting no later than September 30, 2027. The same evening Vantage Data Centers gave up the site of its proposed Trident campus there, a separate event. This piece follows the resolution and its map as printed in the council's agenda packet, with local reporting, as of November 26, 2026. The packet holds the text as proposed; reports of the vote describe the same terms.
What the council passed
| Term | What Resolution R2026-146 says |
|---|---|
| Paused | The "acceptance, process, or approval of any new development application" that would establish a data center "as a primary use", or "expand or otherwise increase the gross-floor area of an existing Data Center" |
| Where | Land "west and south of the intersection of the Aerotropolis Alignment, otherwise currently known as Powhaton Road, and Interstate 70", out to the city limits, "as shown in Exhibit A" |
| Until | Through "the earlier of September 30, 2027, or the date City Council determines that appropriate land use regulations are in place" |
| Exempt | "Development Applications currently pending and other contractual negotiations that were initiated prior to the effective date". The resolution "shall not be applied retroactively" |
| Definition | The city code's: a "facility containing one or more large-scale computer systems used for data storage and processing for off-site users" |
| In effect | It "shall take effect immediately" |
The definition is the one already in Aurora's development code. It has no megawatt or square-foot figure, and "large-scale" is not defined by number. Broomfield's pause, as Colorado Newsline reported on August 10, 2026, applies at 10 MW or more, and most of the Ohio bans in our piece on the November 3 ballot measures start at 25 MW. Aurora draws no such line, so a small colocation or hosting operator has to ask the city what "large-scale" covers.
The mayor and all ten council members are listed as sponsors. The Sentinel reported that the council "voted unanimously for the temporary pause", with Councilmember Curtis Gardner excused.
Coverage differs on two points the text settles. It is a resolution, though one report calls it an ordinance; the ordinance on that night's agenda concerned tax incentives. And "Powhaton Road" and "the proposed Aerotropolis Parkway" are one line: the resolution's "Aerotropolis Alignment" is the proposed parkway, "currently known as Powhaton Road", running north from I-70 along "the Powhaton Road and Jackson Gap alignment".
Where it applies: the map
The words "west and south of the intersection" can be read as the southwest quadrant alone or as everything except the northeast. Exhibit A, the map attached to the resolution, settles it. Its legend has two entries, "Proposed Moratorium Area" and "Exempt Area", and it shows one exempt block: the city's land north of I-70 and east of the alignment, running east past Hudson Road. Everything else inside the city limits is hatched as moratorium area, including the land north of I-70 west of the line, around E-470, and the city's land south of I-70 on both sides of it.
The findings give the reasons: the alignment "creates a natural barrier that protects residential zone districts", and east of it the uses allowed in the Airport, Business/Tech and Industrial districts "are compatible with Data Center operations".
Two shorter descriptions are in circulation. The Denver Gazette reported that Mayor Mike Coffman proposed to "exclude vacant land north of I-70 and east of Powhaton Road", which matches the exempt block. The Colorado Sun's "south of Interstate 70 and west of Powhaton Road" is narrower than the map: it leaves out hatched land north of I-70 and hatched land east of the line.
Zoning does not override the pause. Data centers remain a permitted use in four districts (airport, accident potential zone, business/tech and medium industrial), Colorado Politics reported when the council removed them from a mixed-use district on October 12, 2026. A parcel in one of those districts inside the moratorium area is paused all the same. The Trident site is one.
The project behind the vote
Vantage Data Centers, based in Denver, applied in August 2025 to build Trident on 108 acres at the northwest corner of E-470 and East 48th Avenue, beside the Windler and Green Valley Ranch neighborhoods. Its size is reported two ways: 334 MW, the design figure Vantage gave the Denver Post in October 2026, and 500 MW in the Colorado Sun; When In Your State gives both, as about 334 MW of computing capacity within a total demand of 500 MW. Floor area is about 860,000 square feet according to the Sentinel and Mile High CRE, and 1.5 million according to the Denver Gazette, citing documents in the city's development portal.
The site is in the Airport District, where a data center is a permitted use, and the application was in its fourth round of city review. A draft council resolution put the problem in one clause: "while a data center is a permitted use on the Current Site, it is in close proximity to residential uses". On October 21, 2026, Vantage told the city by letter that it was evaluating other locations and asked for 90 days.
On November 23, 2026, Misty Allen, Vantage's vice president of public policy for North America, said: "While we will no longer pursue the current site for our proposed campus, Vantage remains committed to being a responsible long-term partner in the state." The company named no replacement site.
The withdrawal and the moratorium are separate. On the map the site, just west of E-470, is in the moratorium area, but the Sentinel reported that the pause would not have applied to Trident, because its application had already been accepted. The project left a site where it was both a permitted use and exempt.
Third attempt, narrower each time
The council "twice failed to pass a more comprehensive moratorium that would have covered the entire city", in the Colorado Sun's words. The record:
- August 10, 2026. A resolution pausing new data center applications failed when the council split evenly and Mayor Coffman cast the deciding vote against it. Reports differ on its length: open-ended in the Sentinel's account of the meeting, which says a separate six-month plan was pulled from the agenda; six months according to Colorado Politics and When In Your State. The same night the council voted 7-4 to write data center rules instead.
- September 2026. An evaporative cooling ban got a unanimous first vote on September 14, 2026, Colorado Politics reported. When In Your State reports a ban approved on September 28, 2026.
- October 26, 2026. A motion to bring a citywide moratorium back "failed 6-5 just before midnight", Denver7 reported: six votes in favor, Coffman's now among them, where council rules required seven.
- November 9, 2026. An ordinance ending tax incentives for data centers was approved in study session. A Sentinel report of that date quoted Vantage's Mark Freeman: "No decision has been made to relocate the project."
- November 23, 2026. The partial moratorium passed. Councilmember Alison Coombs called it "limited and imperfect" and said "this is the moratorium we can pass", the Colorado Sun reported. Councilmember Stephanie Hancock, who had opposed the earlier attempts, said, per the Sentinel: "I'm not in favor of the word moratorium, that really bothers me and I think it sends a weird message to businesses."
The rules coming next
- Setbacks and noise. Code changes that the Planning and Zoning Commission approved on November 10, 2026 would bar data centers within 750 feet of residentially zoned land, make them a conditional use out to half a mile, and require a noise study, the Sentinel reported. No council vote date had been reported as of November 26, 2026.
- Tax incentives. Ordinance 2026-60 would end new sales and use tax incentives for data centers. The Sentinel reported a unanimous vote for it on November 23, with one more needed; the packet lists the second meeting for December 7, 2026. Its definition is the one place the words "regardless of the megawatts usage or square footage" appear; the moratorium resolution does not use them.
- Power. The Sentinel reported that the version Coffman first planned "would have prevented data centers from building in the city until they had assurance of power from an energy utility". The resolution carries no such condition.
- State level. The Colorado Sun reported on November 25, 2026 that the Colorado Public Utilities Commission has ordered Xcel Energy to develop data center rates that protect other customers. Xcel's own proposal, announced on April 2, 2026, covers new loads of 50 MW or more. Two data center bills failed in the 2026 Legislature, and the sponsors of one plan to bring legislation back in 2027, Colorado Newsline reported.
Existing incentive agreements stand; the packet calls their value "already committed by agreement". It lists four:
| Operator and site | Rebate, maximum and paid to date |
|---|---|
| J.P. Morgan Chase, 23505 E 6th Ave | 75%; up to $11,317,083; $7,148,913 paid |
| QTS Aurora, 1160 N Gun Club | 40 to 60%; up to $19,088,438; $2,241,100 paid |
| Vantage Data Centers CO21, E-470 and 48th Ave | 50 to 60%; up to $38,925,000; nothing paid, not built |
| NTT Global Data Centers DN1, 48th Ave and Powhaton | 50%; up to $13,597,500; nothing paid, not built |
The city puts the four maximums at $82,928,021 and says $9,390,000 has been rebated since 2021. The Vantage agreement is for the site the company has now left; whether it still has a project behind it is a question for the city.
Not only Aurora
On August 10, 2026, Colorado Newsline listed a one-year moratorium in Denver; Jefferson County's, extended until March; Larimer County's, extended to February; six months in Boulder County from the beginning of June; 18 months in Broomfield; five years in Lochbuie; 18 months in Woodland Park; six months in Monument; and a cap on data center energy use in Longmont. On November 25, 2026 the Colorado Sun named Denver, Boulder County, Longmont and Thornton as having "imposed moratoriums or limited development". The November 3 votes in other states are in our ballot piece.
What operators should check
These are questions for the city's planning staff, not legal advice. The resolution is short and leaves several open.
- The map. Ask for Exhibit A and locate the parcel. Only the block north of I-70 and east of the alignment is exempt.
- The application. Applications pending, and negotiations begun, before November 23, 2026 are exempt. A new one inside the area waits.
- Primary use. The pause covers applications to establish a data center "as a primary use". Ask how the city treats a server room that supports another business on the site.
- Expansion. An application that adds gross floor area to an existing data center is paused. Ask whether more power or cooling inside the existing building needs a development application at all.
- Distance. Outside the paused area, measure to the nearest residentially zoned land against the proposed 750-foot and half-mile bands.
- Cooling and noise. Design without evaporative cooling and expect to supply a noise study.
- Incentives and power. Model the project without a city tax rebate, and bring evidence of utility service: an assurance-of-power condition was in the mayor's earlier version.
- Dates. December 7, 2026 for the second vote on the incentive ordinance; September 30, 2027 as the latest end of the pause; the 2027 legislative session.
If you rent capacity rather than build it
The resolution does not regulate a facility that is already operating, or its tenants. For customers the effect is indirect: if pauses like this slow new supply, existing powered space gets scarcer. "What this does to a server or rack bill" in our piece on the November 3 votes covers how that reaches a price.
Sources
- City of Aurora: Council Meeting Agenda Packet, November 23, 2026 (PDF, 143 MB; Resolution R2026-146 and Exhibit A at PDF pages 1072 to 1075, the draft Trident resolution at 1081, Ordinance 2026-60 at 3147 to 3152)
- Sentinel Colorado: Aurora City Council passes data center moratorium through September 2027 (November 23, 2026)
- Sentinel Colorado: Another proposed Aurora data center moratorium and Trident relocation rule face vote (November 18, 2026)
- Sentinel Colorado: Aurora Mayor Coffman pursues data center moratorium amid calls for new regs, tax-break ban (November 9, 2026)
- Sentinel Colorado: Aurora City Council rejects data center moratorium, approves new rules, water regs (August 10, 2026)
- Colorado Sun: New data centers in Aurora? Not for now, as City Council passes temporary moratorium. (November 25, 2026)
- Denver Gazette: Vantage drops Aurora location for Trident Data Center (November 23, 2026)
- Denver7: Aurora City Council halts effort to reconsider data center moratorium amid Trident project fight (on the October 26, 2026 meeting)
- Mile High CRE: Aurora City Council Approves Data Center Moratorium (November 24, 2026)
- Yahoo News (When In Your State): Colorado city temporarily blocks new data centers after months of community opposition (November 26, 2026)
- Kiowa County Press (The Center Square): Aurora imposes temporary data center moratorium in an area (November 25, 2026)
- GovTech (The Denver Post): Aurora, Colo., Mayor Says Hyperscale Data Center Must Be Stopped (October 6, 2026)
- Colorado Politics: Aurora moves forward with ban on data center tax incentives (November 9, 2026)
- Colorado Politics: Aurora City Council votes down indefinite data center moratorium (October 26, 2026)
- Colorado Politics: Aurora City Council bans data centers in mixed-use office zones (October 13, 2026)
- Colorado Politics: Aurora bans evaporative cooling for data centers, turf installation to save water (September 14, 2026)
- KUNC (Colorado Newsline): Local governments in Colorado enact moratoriums on data center development (August 10, 2026)
- Xcel Energy: Xcel Energy proposal protects customers from higher bills as data center demand grows (April 2, 2026)